Special Finance and General Purposes Special Minutes 11 July 2024
Special Finance and General Purposes Committee Minutes 11 July 2024
Corporation and Committee Minutes- Special Finance and General Purposes Committee Minutes 11 July 2024
Minutes of a special meeting of the board of Leicester College corporation: Finance and general purposes committee
Held on 11 July 2024 online via MS
Present: Danielle Gillett (Chair), Chan Kataria, Lesley Giles, Lee Soden, Verity Hancock
In Attendance: Louise Hazel - Director of Governance and Policy, Shabir Ismail - Deputy Principal/CEO, Shaun Curtis - Director of Estates and Campus Services
- Declarations of interest - Verity Hancock declared an interest as a member of the Office for Students (OfS) Board. 
 
- Apologies for absence - Apologies for absence were received from Robert Radford 
 
- Capital projects update - Aeronautical - 3.1 The Deputy Principal and Director of Estates and Campus Services presented - an update on the aeronautical project. The following points were highlighted. - 3.1.1 The budget remaining for the project, funded by the OfS, was £4.34m - after other projects had been completed. Tenders had been invited from - six potential contractors, two of which had withdrawn. The four remaining - tenders had come in at between £4.38m and £5.02m net. 
- 3.1.2 Value engineering had brought prices down with GF Tomlinson’s tender - at £4.124m and it was proposed to proceed with GF Tomlinson as the - best priced tender. The company had recently completed a £15m - aeronautical and space institute for Lincoln College. 
- 3.1.3 Taking into account gross costs and a contingency of £125k, the total - cost of the project would be £5.074m. A further £125k of furnishings - fittings and equipment could be saved leaving a shortfall of £859k. 
- 3.1.4 It was proposed to vire £374k from the capital budget set aside for - roofing works to this project; the roofing works could be deferred. This - meant an additional £475k was needed from reserves to cover the - shortfall and enable the project to proceed. The Committee was asked to - agree the additional capital expenditure. 
- 3.1.5 The College would now be contributing 20% of the project cost with the - remaining 80% from the OfS. 
 
- 3.2 Governors asked a number of questions including: - 3.2.1 What the original planned College contribution was. It had been - 10%. 
- 3.2.2 What would happen if the additional capital expenditure was not - agreed? The Committee could choose not to agree it but this would - restrict growth and the ability to enter an area of delivery which was - lucrative and would be a genuine USP for the College. There was no - Level 4/technical pathway for space. It was frustrating that the LLEP - and other local bodies had not seen the benefits and supported the - plans with funding. 
- 3.2.3 The College should push for more funding from the OfS. It would - continue to do so although the OfS had indicated that no additional - funding was available. 
- 3.2.4 The cost increases were always going to be likely given the current - market but the project should go ahead. Noted. It was possible that - more funding might become available. 
- 3.2.5 The new government’s approach looked promising with the - potential for an industrial strategy, priority sectors including high - level engineering, strengthened devolution and local investment, all - of which might unlock opportunities for further funding. 
- 3.2.6 The College should make it known to anyone who might be able to - provide funding that additional funding was needed so that should - funding become available the project was an obvious choice. There - was nothing to lose in doing so. The College was working with the - University of Leicester. It would also make clear to the OfS that not - getting additional funding might mean the project needed to be scaled - down. The Vice Principal would be meeting with Phoebe Dawson - (Leicester and Leicestershire Business and Skills Partnership) soon and - would raise it with her. 
- 3.2.7 Was there any scope for working with Leicester University to - identify a named sponsor? This could be explored. 
- 3.2.8 The short term versus the long term needed to be considered. - There was a good case that this was integral to growth although - there were no guarantees. What would the impact be on the bottom - line, the EBITDA and the financial rating? This was capital - expenditure so there would only be a small hit on the bottom line in - terms of depreciation. The EBITDA would be slightly weakened but not - to any significant extent and the financial health would still be good. 
- 3.2.9 Previously the College had been bold and taken decisions to invest - out of a position; this was a similar situation and there was the - potential for access to funding which might not be available again. - Agreed. 
- 3.2.10 Based on previous experience, was there confidence that the - contingency was sufficient? The greatest point of uncertainty was - usually at the tender stage; once the contract was awarded, the - architects who had worked with the College before and knew the market - well would be critical in helping control costs. Having previously built the - motor vehicle block next to site of the new building, there was also - confidence that there were unlikely to be any unknowns in respect of the - land. There were no archaeological issues. Since it was a new building - here would be no need to decant which could add to delays. 
- 3.2.11 Why was a decision needed now? The preferred contractor required a - purchase order to be raised by 12 July in order to commit to the project - and start work. A meeting with the architect would also be taking place - on 12 July. The Committee needed to approve the proposed expenditure - above the previously agreed capital budget. 
- 3.2.12 Had sufficient due diligence been undertaken on the contractor and - did they have the capacity to deliver? There had been some issues - with the company’s delivery of reactive work in other sectors. The - company had two divisions and the building division was considered low - risk. Its recent work at Lincoln College on a similar project provided - some reassurance of its capacity to deliver. 
 
- 3.3 The committee: - 3.3.1 Noted the tender prices received for the aeronautical project. 
- 3.3.2 Approved the additional spend of £859k on the project through - cash reserves, £384k of which would be vired from another project. 
- 3.3.3 Requested a report back at the next meeting. 
 
 
- Date of next meetings - 3 October 2024